SECMP 0018: Standard Electricity Distributor Configuration Settings

Date raised 23/06/2016 Modifications Path Path 3 – Self Governance
Current stage Modification Report Overall status Awaiting Implementation
Refinement? Yes Urgent modification? No
Proposer name Alan Creighton Proposer's organisation Northern Powergrid

Summary

Amendments to the Great Britain Companion Specification (GBCS) to specify the standard Electricity Distributor configuration settings to be applied to an electricity smart meter by the Manufacturer. Application of default configuration settings will reduce the need for Electricity Distributors to apply settings immediately after commissioning.

Latest Progress

The Change Board originally approved this modification for implementation in the June 2019 SEC Release. On 15 March 2019, the Panel agreed to request this modification be moved to the November 2019 SEC Release, to align all GBCS changes into a single release. The Authority approved this request on 29 March 2019.

Proposed implementation timetable

Modification Proposal raised: 23 June 2016

Panel considers Initial Modification Report: 08 July 2016

Working Group Consultation: 18 June 2018 - 06 July 2018

Draft Modification Report first presented to Panel: 13 July 2018

First Modification Report Consultation: 16 July 2018 - 06 August 2018

Change Board vote: 22 August 2018 - voted to send back to the Panel

Updated Modification Report presented to Panel: 14 December 2018

Second Modification Report Consultation: 17 December 2018 - 10 January 2019

Change Board vote: 23 January 2019

Implementation date

07/11/2019

Documents

  • Modification Proposal Raised
  • Initial Modification Report
  • Refinement Process
  • Modification Report
  • Change Board Vote
  • Modification Decision
SECMP0018 - Proposal Form
24/06/2016
SECMP0018 - Initial Modification Report
14/07/2016
SECMP0018 - Draft Solution Design Document - Draft
15/12/2016
SECMP0018 - WG Meeting 1 - Final Minutes
09/07/2018
SECMP0018 - Working Group Consultation
18/06/2018
SECMP0018 - Working Group Consultation Responses
11/07/2018
SECMP0018 Modification Report Consultation
16/07/2018
SECMP0018 Modification Report Consultation Responses
07/08/2018
SECMP0018 Second Modification Report Consultation
17/12/2018
SECMP0018 Change Board Vote
24/01/2019
Request to change the implementation date for SECMP0018
19/03/2019
Ofgem Decision Letter on Change of Implementation Date for SECMP0018
29/03/2019

If you believe there is a problem with this modification, please let us know HERE.

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close