MP122B Operational Metrics – Part 2

Proposer Gemma Slaney (National Grid Elect Distribution)
Lead Analyst SEC Change
Date raised 11/09/2020
StageImplemented
Implementation date 2 November 2023 (November 23 SEC Release)
Latest update On 23 November 2022 the Change Board voted to approve this modification for implementation. This modification was implemented as part of the November 2023 SEC Release.

What is the issue?

Issues with transparency of reporting and relevance of the measures contained within the DCC Performance Measurement Report (PMR) have arisen. In its monthly review of the PMR, the Operations Group has found it increasingly difficult to report to the Smart Energy Code (SEC) Panel on the issues within the report.

As a result of the issues encountered, the Operational Metrics Review (OMR) was undertaken to better understand the PMR measures, consider amendments and recommendations of new performance indicators. Through workshops and User surveys, it is clear that Users want to see reporting that reflects the business processes that the DCC supports.

What is the solution?

To realise the full set of reporting sought, changes are needed to the DCC Systems and Service Provider contracts. To ensure the reporting elements that did not require these changes could be delivered sooner, the original modification was split into two and progressed under MP122A ‘Operational Metrics’. MP122B seeks to progress the DCC System and Service Provider changes to improve reporting on several business processes as well as improve the timeliness of the PMR.

Who is impacted?

DCC

What SEC documents are affected?

Section H 'DCC Services'

Timeline

11 Sep 2020
Modification split into MP122A and MP122B
26 May 2021
DCC Preliminary Assessment returned
08 Jun 2021
Modification discussed with Working Group
05 Aug 2021
to
03 Sep 2021
Refinement Consultation
08 Oct 2021
Modification discussed with Working Group
11 Feb 2022
Modification discussed with Working Group
24 Feb 2022
to
11 Jul 2022
DCC Impact Assessment
05 Sep 2022
to
23 Sep 2022
Second Refinement Consultation
18 Oct 2022
Modification Report approved
19 Oct 2022
to
09 Nov 2022
Modification Report Consultation
23 Nov 2022
Modification approved for implementation

Modification documents

MP122B Conclusions Report
23/11/2022
MP122B Modification Report Consultation
18/10/2022
MP122B Modification Report v1.1
18/10/2022
MP122B Legal Text v1.0
18/10/2022
MP122B Second Refinement Consultation responses
30/09/2022
MP122B Second Refinement Consultation
05/09/2022
MP122B DCC Impact Assessment - CR4445
05/09/2022
MP122B DCC Impact Assessment - CR4392
05/09/2022
MP122B Working Group meeting summary - August 2022
16/08/2022
MP122B February 2022 Working Group Meeting summary
21/02/2022
MP122B October 2021 Working Group Meeting summary
20/10/2021
MP122B Refinement Consultation responses
14/09/2021
MP122B Refinement Consultation
05/08/2021
MP122B Preliminary Assessment v1.3
27/07/2021
MP122B June Working Group Meeting summary
23/06/2021
MP122B April Working Group Meeting summary
07/05/2021
MP122A-B January Working Group Meeting summary
15/02/2021
MP122B DCC Change Request questionnaire responses
15/01/2021
MP122A-B December Working Group meeting summary
04/01/2021
MP122B - DCC Change Request questionnaire
08/12/2020
MP122B business requirements v1.4
03/12/2020
MP122A-B October Working Group Meeting summary
22/10/2020
No files
No files
No files
No files
No files

If you believe there is a problem with this modification, please let us know HERE.