SECMP 0035: Updates to SEC Appendix B – Organisation ARL expiration date to be aligned to DCCKI ARL

Date raised 03/05/2017 Modifications Path Path 3 – Self Governance
Current stage Not Applicable Overall status Accepted - implemented
Refinement? No Urgent modification? No
Proposer name SMKI PMA Proposer's organisation SMKI PMA

Summary

This modification looks to ensure that the Smart Metering Key Infrastructure (SMKI) Organisation Authority Revocation List (ARL) is aligned to the Data Communications Company Key Infrastructure (DCCKI) ARL; amending the expiration date of the Organisation ARL from 12 months to 13 months, as per the DCCKI Certificate Policy (CP) and the DCCKI ARL.

Proposed implementation timetable

Modification Proposal raised: 03 May 2017

Panel considers Initial Modification Report: 12 May 2017

Modification Report Consultation: 17 May 2017 - 08 June 2017

Change Board vote: 21 June 2017

Implementation date

12/07/2017

Documents

  • Modification Proposal Raised
  • Initial Modification Report
  • Refinement Process
  • Modification Report
  • Change Board Vote
  • Modification Decision
SECMP0035 - Modification Proposal Form v1.0
05/05/2017
SECMP0035 Initial Modification Report v1.0
17/05/2017
No files
SECMP0035 Modification Report Consultation v1.1
23/05/2017
SECMP0035 FMR
27/06/2017
SECMP0035 FMR
14/07/2017
SECMP0035 FMR
14/07/2017

If you believe there is a problem with this modification, please let us know HERE.

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close