SECMP 0004: Inclusion of Device Serial Number data item in the Smart Metering Inventory

Date raised 19/02/2016 Modifications Path Path 2 – Authority Determination
Current stage Not Applicable Overall status Rejected
Refinement? Yes Urgent modification? No
Proposer name Paul Saker Proposer's organisation EDF Energy

Summary

Addition of Device Serial Number in the Smart Metering Inventory to enable mapping between data held in the DCC systems, and industry dataflows.

SECMP0004 is out for a second Modification Report Consultation. Responses are due by EOB 7th August .

On the 2nd June 2017, the Authority (BEIS) issued a decision letter sending SECMP0004 back for further work. The letter sets out that they are unable to make a decision at this time and required details on the following:

- Further detail on the business case of the Modification Proposal to the Proposer;
- Further detail of the cost, benefits and impacts of the modification on industry (including the DCC) and a balanced assessment of the associated benefits (both qualitative and quantitative);
- Consideration of the viability of the proposal, specifically the availability of the information that needs to be supplied to support the back-filling of Device Serial Number data within the Smart Metering Inventory;
- Further consideration of other alternative solution to achieve the principle aim of the Modification Proposal, including a comparison of the costs, benefits, risks and impacts (where possible).

In addition the Authority have requested a revised implementation date in light of the indications from the DCC that they cannot implement Modification Proposal prior to 2019. The Authority letter which provides the full details on why SECMP0004 has been sent-back is available under the Modification Decision chevron below.

The Panel considered the Send-Back at its June meeting. The Panel agreed an approach to take which will take the form of a further consultation with SEC Parties, to obtain extra input on the case for the modification. The consultation was issued on 17th July 2017, following receipt and confirmation from the DCC on when it could implement the Modification Proposal in 2019, if approved.

On the 23rd August 2017, the Change Board did not reach the majority required to recommend the approval of SECMP0004, and therefore recommended it's rejection. Following the vote, SECAS issued the Final Modification Report to BEIS for Authority Determination. On the 29th September 2017, BEIS decided to reject SECMP0004.

Proposed implementation timetable

Modification Proposal raised: 19 February 2016

Panel considers Initial Modification Report: 11 March 2016

Working Group Consultation: 07 November 2016 - 28 November 2016

Panel considers Draft Modification Report: 10 March 2017

Modification Report Consultation: 17 July 2017 - 07 August 2017

Change Board vote: 23 August 2017

Authority Decision: 29 September 2017

Implementation date

29/09/2017

Documents

  • Modification Proposal Raised
  • Initial Modification Report
  • Refinement Process
  • Modification Report
  • Change Board Vote
  • Modification Decision
SECMP0004 - Modification Proposal Form
13/04/2016
SECMP0004 - Initial Modification Report
13/04/2016
Working Group 2 - 01 Business Requirements & Minutes
31/05/2016
Working Goup 2 - 02 Business Requirements
09/06/2016
SECMP0004_DCC_Preliminary Impact Assessment v1.1
27/06/2016
SECMP0004 Solution Design Document v4
19/10/2016
SECMP0004 Solution Design Document v6
17/11/2016
SECMP0004 - Impact Assessment v2.0
02/12/2016
SECMP0004 - Working Group Meeting 1 - Final Minutes
14/02/2017
SECMP0004 - Working Group Meeting 2 - FInal Minutes
14/02/2017
SECMP0004 - Working Group Meeting 3 - Final Minutes
14/02/2017
SECMP0004 - Working Group Meeting 4 - Final Minutes
14/02/2017
SECMP0004 - Working Group Meeting 5 - Final Minutes
14/02/2017
SECMP0004 - Impact Assessment v3.1
02/03/2017
SECMP0004 - Impact Assessment v3.2
13/03/2017
SECMP0004 - Modification Report
15/03/2017
SECMP0004 - Modification Report Attachment A - Solution Design and Legal Text v7.
15/03/2017
SECMP0004 - Modidication Report Attachment B - Working Group detailed considerations (white)
15/03/2017
SECMP0004 - Modification Report Attachment C - Modification Report Consultation Response Form
15/03/2017
SECMP0004 - Final Modification Report
11/04/2017
SECMP0004 - Final Modification Report Attachment A - Solution Design and Legal Text
11/04/2017
SECMP0004 - Final Modification Report Attachment B - Working Group detailed considerations
11/04/2017
SECMP0004 - Final Modification Report Attachment C - Modification Report Consultation Responses
11/04/2017
SECMP0004 - Final Modification Report Attachment A - Solution Design and Legal Text v7.1
21/04/2017
SECMP0004 - Final Modification Report Attachment B - Working Group detailed considerations
21/04/2017
SECMP0004 - Final Modification Report Attachment D - Change Board vote outcome
21/04/2017
SECMP0004 - Final Modification Report (Post CB vote)
26/04/2017
SECMP0004 - Final Modification Report Attachment C - Modification Report Consultation Responses
26/04/2017
2017 06 02 Modification proposal 0004 - Authority Decision
05/06/2017
SECMP0004 - Second Modification Report consultation
17/04/2017
SECMP0004 Authority Decision
02/10/2017

If you believe there is a problem with this modification, please let us know HERE.

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close