SECMP 0023: Correct Units of Measure for Uncontrolled Gas Flow Rate

Date raised 26/10/2016 Modifications Path Path 2 – Authority Determination
Current stage Not Applicable Overall status Awaiting Implementation
Refinement? No Urgent modification? No
Proposer name Mark Pitchford Proposer's organisation RWE npower

Summary

Currently GBCS limits the values of the Uncontrolled Gas Flow rate to be in whole numbers of m3. This modification proposes to change that to allow m3 with accuracy to 3 decimal places to be specified.

Proposed implementation timetable

Modification Proposal Raised: 26 October 2016

Initial Modification Report presented to Panel: 11 November 2016

Working Group Consultation: 27 February 2018 - 20 March 2018

Draft Modification Report presented to Panel: 13 April 2018

Modification Report Consultation: 19 April 2018 - 11 May 2018

Change Board Vote: 23 May 2018

Implementation date

07/11/2019

Documents

  • Modification Proposal Raised
  • Initial Modification Report
  • Refinement Process
  • Modification Report
  • Change Board Vote
  • Modification Decision
SECMP0023 - Modification Proposal Form v1.0
03/11/2017
SECMP0023 - Initial Modification Report v1.0
14/11/2016
SECMP0023 - Solution Design Document v0_4
21/12/2016
SECMP0023_DCC_ PA_v1.0
25/04/2017
SECMP0023_WG_02_2404 - Final Meeting Headlines v1.0
18/05/2017
SECMP0023_DCC_Full Impact Assessment v1.1
12/02/2018
SECMP0023 Working Group Consultation Responses
22/03/2018
SECMP0023 Modification Report Consultation
19/04/2018
SECMP0023 Modification Report Consultation Responses
17/05/2018
SECMP0023 Final Modification Report
24/05/2018
SECMP0023 Decision Document
24/05/2018
Request to change the implementation date for SECMP0023
15/08/2018
Response to request to change the implementation date for SECMP0023
24/08/2018
Updated request to change the implementation date for SECMP0023
20/09/2018
Direction to change the implementation dates for SECMP0006, SECMP0008, SECMP0023 and SECMP0048
28/09/2018
Request to change the implementation date for SECMP0023
15/01/2019
Ofgem Decision Letter on Change of Implementation Date for SECMP0023
30/01/2019

If you believe there is a problem with this modification, please let us know HERE.

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close